Building Reserve and Using KWH

Collapse
X
 
  • Time
  • Show
Clear All
new posts

  • foo1bar
    replied
    Originally posted by bcroe
    These wires will not be used at anything like current capacity, the idea is oversize to control loss over a long run. Bruce Roe
    The POCO here uses something similar to what you see if you search for "Polaris IT-250". The version they used had 4 ports, and was more water-tight I think. But since you're going to be above ground (theirs was underground), and only doing a simple size change, not branching, the IT-250 or ISR-250 are probably more appropriate.

    I've also seen description in this forum of a crimped-on "pin terminal" to change sizes to fit into a breaker's input. So that might be an option - or a crimped on reducer to change sizes.

    If you go with a split bolt, I would make sure it's rated for aluminum.

    I don't know the other thing you have in the picture. But I think you're right to make sure you understand the proper way to use them before you use it.

    Leave a comment:


  • Ampster
    replied
    Originally posted by bcroe

    I see some things like this AMP B1-T which is rated to connect 4/0 aluminum to
    copper. Drive that wedge in I guess. There are also some big rated larger versions
    of this split bolt available. If these work, what is the prep process and anti oxident to
    use in the process?
    I would use a split bolt because I wouldn't trust a wedge to stay under various temperature changes. . If the copper and aluminum are fresh just cover them with antioxident. I use a product called NoAlox. Often available at Home Centers under Ideal or Gardner Bender brands. Electrical supply houses carry it too.

    Leave a comment:


  • bcroe
    replied
    Originally posted by bcroe
    direct burial 4/0-4/0-2/0 aluminum cable

    The question then is how to terminate it. Could it come up through conduit, to an
    outside box, then convert to smaller copper to the building?
    I see some things like this AMP B1-T which is rated to connect 4/0 aluminum to
    copper. Drive that wedge in I guess. There are also some big rated larger versions
    of this split bolt available. If these work, what is the prep process and anti oxident to
    use in the process?

    Soldering aluminum can be done, except it may not work for big wire. Comments?

    These wires will not be used at anything like current capacity, the idea is oversize
    to control loss over a long run. Bruce Roe

    40splice.JPG

    Leave a comment:


  • bcroe
    replied
    I used to worry about all HVAC functions being centralized, both the propane furnace and
    the air conditioner relied on that furnace blower. One failure there and I was SOL. That
    problem is gone, with 4 mini split zones, backed up by some substantial resistance heaters
    if ever needed. So the blower is never triggered by the central plant anymore.

    BUT I have an electrostatic air filter I would like operated regularly. And a little air mixing
    between zones could be useful. A brand new blower motor is in place, and the solar PV
    provides plenty of energy to run the motor.

    SO a new function is tagged onto the central furnace. The blower may be run for a set
    time (12 to 60 minutes), and then paused a set time (12 to 120 minutes). This repeats,
    unless set to OFF.

    Here is the control, which just attaches to the 24VAC thermostat circuit. Next winter will
    check it out. Bruce Roe


    blowerF.JPGblowerR.JPG
    Last edited by bcroe; 08-27-2019, 09:53 AM.

    Leave a comment:


  • Ampster
    replied
    Most of the 4/0 cables I have done are DC cables with hydraulic crimps. They bolted to either a battery pack or the inverter. I did connect some 4/0 cable to a service entrance but it already had lugs. You would have to see what kind of connection devices are available at your local supply house. One West Coast supply house that I have used in the past, does have 4/0 cable connecting blocks.

    Now that I am reminded it is direct burial and that you have inclement weather in the winter you might consider a 3 or 4 inch LB into the house and have the junction box inside if that works better. I don't know enough about the details of your house to offer anything more substantial. There are probably several mechanical solutions. As far as the aluminum to copper connection I use Noalox.
    Last edited by Ampster; 08-23-2019, 12:14 PM.

    Leave a comment:


  • bcroe
    replied
    Originally posted by Ampster
    You are not going to want pull 4/0 through more than a couple of long sweeps. I would
    terminate in a big j box and go out the back of that to the building.
    For direct burial the only pulling 4/0 will be through a couple feet bringing it out of
    the ground. Tell me about a suitable aluminum/copper J box. On the very short
    run into the house to a 100A breaker, I could use 2 gauge copper. Bruce Roe

    Leave a comment:


  • Ampster
    replied
    Originally posted by bcroe
    .....

    The question then is how to terminate it. Could it come up through conduit, to an
    outside box, then convert to smaller copper to the building? Bruce Roe
    You are not going to want pull 4/0 through more than a couple of long sweeps. I would terminate in a big j box and go out the back of that to the building.

    Leave a comment:


  • bcroe
    replied
    One item of loss here, is the original 600 foot loop of 4 gauge wire my inverters feed
    the line through. The wire is not operating near capacity. But besides high voltage
    problems, this may be loosing around 1000 KWH a year in resistive heating. The
    thought lately is use direct burial 4/0-4/0-2/0 aluminum cable instead, 24 inches deep.

    The question then is how to terminate it. Could it come up through conduit, to an
    outside box, then convert to smaller copper to the building? Bruce Roe

    Leave a comment:


  • bcroe
    replied
    At this point the annual energy device upgrades are in place and ready for another IL winter. The
    3 mini splits installed 2018 have been able to cool the 2000 sq ft ranch plus the partially exposed
    2000 sq ft basement, and keep it toasty down to 0 deg F outside. There are several resistance
    heaters backing these up in case we see a repeat of -31 F. Backing that up is a propane furnace I
    have not used in a while, but could be run by a gasoline genset if power went away. Surplus KWH
    energy will again be monitored.

    This summer the house mini split capacity was increased 50% by adding one larger unit, and
    another of these was put in the car shop to keep it cooled in summer and hopefully at least above
    freezing all winter. It is surprising how little these need to run in the summer. With 5 minis and
    a dehumidifier on line, 80% of PV generation is still going toward net metering winter reserve. A
    new blower motor in the central furnace will reliably aid circulating any uneven temp air, along
    with the new electrostatic air filter.

    Here is the last mini to go on line, rated effective to -20 F. Still some clean up work needed covering
    the freon lines. Normally I consider it a very amateur thing to just coil up extra length, instead of
    cutting it to exactly the length needed. But this unit specified a minimum 10 foot length, so a 10 foot
    line set was installed unmodified.


    Mini52.JPG


    One thing learned this spring, is that any tubing joints need to be brazed,
    not soldered. With the very high pressure and the thermal cycling, this
    joint pulled apart after some 9 months of operation. Bruce Roe

    MiniLineJoint.JPG

    Leave a comment:


  • azdave
    replied
    I want to be like Bruce! (sort of)

    Mini-split installed here too but a cooling-only unit to maximize our solar reserve in the summer heat. Working out nicely now that it has hit 110 here in Phoenix. Keeps the master bedroom and bath a very comfortable temperature while we sleep. The rest of the house is not cooled overnight. Usually, this is the time of year where we start eating into the small reserve that unfortunately gets reset on May 1st. Yesterday was 110 and yet we still banked 20kWh. July and August, when the monsoon season is upon us, will reveal the real value of not cooling the entire house all night long.
    Last edited by azdave; 08-08-2019, 09:02 AM.

    Leave a comment:


  • Ampster
    replied
    Originally posted by bcroe
    ............
    Just what is the right amount of annual
    generation is hard to say, because winter weather is so variable. Bruce Roe
    That is a good reason for an aggressive design.

    Leave a comment:


  • bcroe
    replied
    The mini split R410A inverter driven compressor technology has such a long list of
    improvements over what proceeded it, it ought to be replacing equipment (where
    applicable) on a huge scale. But there seems to be some resistance in the US HVAC
    industry to them. I am doing some volunteer work on a century old solid concrete
    mansion, now on the nat register. I just got the job of an extensive energy audit of all
    the buildings. Have not started yet, but high on my hit list is a huge old AC unit sitting
    on an intermediate roof, to supplement some rooms in the steam heat main building.

    These units run 450psi high side, 240psi low side, more than double my R12 stuff.

    My place has been highly experimental, but it feels like solutions to all main issues
    have been found. Perhaps once all my HVAC equipment is updated and the rest of
    the panels are remounted, it will be finished. Just what is the right amount of annual
    generation is hard to say, because winter weather is so variable. Bruce Roe
    Last edited by bcroe; 06-12-2019, 10:36 PM.

    Leave a comment:


  • Ampster
    replied
    Originally posted by J.P.M.

    For most folks - not Bruce - rather than looking for ways to utilize overproduction, some might think it might be better yet to size the equipment so that the excess production isn't generated in the first place.
    I don't get the impression that this project has been completed yet. I has been going for at least 15 months with a stated goal of being Net Zero. I think it is too early to say that long term there will be excess production.
    Last edited by Ampster; 06-12-2019, 09:41 PM.

    Leave a comment:


  • frankge
    replied
    jumping on the minisplit bandwagon. In Tampa we run AC 24x7 in the warmer months which is a good part of the year. I installed a 12000btu Pioneer minisplit for our master bedroom which allows me to basically turn off the new 2 stage heatpump with ECM blower I just installed. That along with a heatpump water heater has given me a net-zero electric consumption. They raised our rates and electric s still cheap compared to some of you - 14 cents per Kwh, but I've already seen it raise from 12 cents. Btw the cost to install the minisplit myself end to end was about $800.00

    Leave a comment:


  • J.P.M.
    replied
    Originally posted by Ampster
    Sounds like a good plan to utilize some of that 4 gWhrs of energy your system produces over and above your consumption..
    For most folks - not Bruce - rather than looking for ways to utilize overproduction, some might think it might be better yet to size the equipment so that the excess production isn't generated in the first place.

    Leave a comment:

Working...