  • J.P.M.
    Solar Fanatic
    • Aug 2013
    • 15036

    #46
    Originally posted by ChrisBarrett
    I actually called Ironridge, and they said they have a tech brief that notes that the flashing passed all tests with no sealant at all. So... I'm just putting sealant in the hole and I'll check the attic on the first big rain and see if there are any leaks.
    Info from an outfit with skin in the game. What tests ? Kind of like when Ford said their Pintos didn't explode when hit from behind.

    Keep checking. Sealant dries out/changes dimension as f(time, operating conditions).

    Comment

    • bob-n
      Solar Fanatic
      • Aug 2019
      • 569

      #47
      The Ironridge instructions call for sealant in the hole. To me, that sounds unnecessary, because the lag and the wood will form a very tight connection. Ironridge doesn't show sealant around the bottom of the flashing, but that's what everyone I know does, too. As Mike said, a half-circle around the bolt center. The theory is that this will divert water downstream. It doesn't prevent water from getting upstream, but makes it much less likely. It's all about getting the odds in your favor. Things do go wrong. The more things you have as backup without screwing up the system, the better.

      I hate working with roof sealant.
      7kW Roof PV, APsystems QS1 micros, Nissan Leaf EV

      Comment

      • Mike90250
        Moderator
        • May 2009
        • 16020

        #48
        Originally posted by bob-n
        .... I hate working with roof sealant.
        Finish it.

        I hate working with roof sealant in the rain.


        Powerfab top of pole PV mount (2) | Listeroid 6/1 w/st5 gen head | XW6048 inverter/chgr | Iota 48V/15A charger | Morningstar 60A MPPT | 48V, 800A NiFe Battery (in series)| 15, Evergreen 205w "12V" PV array on pole | Midnight ePanel | Grundfos 10 SO5-9 with 3 wire Franklin Electric motor (1/2hp 240V 1ph ) on a timer for 3 hr noontime run - Runs off PV ||
        || Midnight Classic 200 | 10, Evergreen 200w in a 160VOC array ||
        || VEC1093 12V Charger | Maha C401 aa/aaa Charger | SureSine | Sunsaver MPPT 15A

        solar: http://tinyurl.com/LMR-Solar
        gen: http://tinyurl.com/LMR-Lister

        Comment

        • Ampster
          Solar Fanatic
          • Jun 2017
          • 3658

          #49
          Originally posted by ChrisBarrett
          I actually called Ironridge, and they said they have a tech brief that notes that the flashing passed all tests with no sealant at all. So... I'm just putting sealant in the hole and I'll check the attic on the first big rain and see if there are any leaks.
          I would feel comfortable following the Manufacurers instructions. They have a good reputation and want to protect that reputation. Hopefully their tests include, "capillary, turgor pressure as related to osmatic processes, not to mention adhesion and the effects of surface tension."
          The best advice I received many years ago from an civil engineer is that you can't make buildings waterproof, but you can design them to shed water as rapidly as possible.
          9 kW solar, 42kWh LFP storage. EV owner since 2012

          Comment

          • ChrisBarrett
            Member
            • Jun 2020
            • 37

            #50
            Update on the flashing and sealant - i installed with sealant in the hole, as well as a glob on top. We've gotten a couple of monsoon level downpours this week and NO LEAKS! yay.

            Comment