Hi Everyone
Looking to start my long awaited project in the next few weeks.
I have a contract for 50 panels 350w or 17.75kw system.
Here is the problem. I have a two transformer on the power company pole that provides me with 1 200amp 3 wire 240 delta.
Then I have 2 200amp services that are pulled from the low legs of the delta with a third wire ground. All of these go to separate breaker panels.
I was going to use a 15kw 3 phase inverter but with 240 three wire no neutral I have not found one that will work.
So is my best option to use 3 5kw single 240 inverters?
I would have to have a strange animal for my project.
Thanks Neal
Looking to start my long awaited project in the next few weeks.
I have a contract for 50 panels 350w or 17.75kw system.
Here is the problem. I have a two transformer on the power company pole that provides me with 1 200amp 3 wire 240 delta.
Then I have 2 200amp services that are pulled from the low legs of the delta with a third wire ground. All of these go to separate breaker panels.
I was going to use a 15kw 3 phase inverter but with 240 three wire no neutral I have not found one that will work.
So is my best option to use 3 5kw single 240 inverters?
I would have to have a strange animal for my project.
Thanks Neal