Originally posted by Ampster
View Post
lI would tighten the connector bolts between the aluminum rails and beams.
As far as documenting the SR rails ability to span the distance, the Iron Ridge site should help. If you haven't dug the holes and poured the concrete yet, you might be able to move them closer to cantilever the rails a little more. That will allow you to shorten the span.
Comment