I have a 72 cell 330W panel, TriStar MPPT 60, with 2x12volt batteries setup for 24volt. Does this sound about right?
60A between my panel and my CC, 30A between my batteries and CC, and then coming off my batteries with my load circuit and putting a 5A and 10A breaker for the various equipment. The TriStar MPPT 60 model does not have 'load' terminals, so it only makes sense that I bring two separate +/- cables off the batteries and into the various breakers for the load side equipment.
60A between my panel and my CC, 30A between my batteries and CC, and then coming off my batteries with my load circuit and putting a 5A and 10A breaker for the various equipment. The TriStar MPPT 60 model does not have 'load' terminals, so it only makes sense that I bring two separate +/- cables off the batteries and into the various breakers for the load side equipment.