Guest repliedSounds like it could be a warped rotor, if you can see through the wheels then check to see if there are spots on the rotor that look different. I don't have the words to explain but you should be able to see it with your eyes if they are warped very bad.Leave a comment:
-
I understand reality and that scenario well, but understanding something is not the same as condoning it by acquiescence or as inevitable in a race to the ethical bottom.Leave a comment:
-
Solar Racking failure 3.jpg
Some failures are worse than others. Wonder if the bean counters cut some corners here?Leave a comment:
-
Maybe or maybe not. I have met PE's that have bent the rules and let some things slide because if they pushed back they would be out of work and no longer able to use their stamp. Sad but true.
That's one reason why design reviews and such are done. You, I and most all responsible tech. folks know crap like that happens, probably all too often, but I'll be damned if any P.E. worth their nads would knowingly allow such shenanigans (once discovered) to take place under their stamp and call themselves worthy of the title or responsibility of "engineer".Leave a comment:
-
Agree that no one should get a pass on designs like this. I'd add that in at least a few cases I know of, tile hooks were used because the homeowner did not want to "have their tile full of holes" (or have to remove tiles as with some of the newer systems.) That puts pressure on the installer to choose the more marginal system.2.) I'm not implying you are giving anyone a pass here, but because bad engineering happens all the time is no reason to give it a pass when it occurs in situations such as this.
3.) My guess is that a lot of tile hooks on roofs will be just fine, but most of that OKness will be the result of the conservative assumptions and methods that are used to estimate design loads such as wind speeds that may never occur, or embedment lengths for lag screws, etc., or any number of other such things. Some of what I've seen as an engineer gave me a greater appreciation for things like factors of safety, but also continues to make me wonder just how much more of what passes for today's engineering is chewing into that built in conservativeness than prior engineering chewed into that conservativeness.
As a semi qualitative statement, IMO only, tile hooks are probably marginally adequate, but the probability of failures with tile hooks will be higher than other methods.
Leave a comment:
-
That's one reason why design reviews and such are done. You, I and most all responsible tech. folks know crap like that happens, probably all too often, but I'll be damned if any P.E. worth their nads would knowingly allow such shenanigans (once discovered) to take place under their stamp and call themselves worthy of the title or responsibility of "engineer".I have found that issues with structures that have failed usually are not the responsibility of the engineer who designed it but of the person in charge of the project finances.
Those that hold the purse strings seem to find ways to cut corners regardless of the outcome.Leave a comment:
-
I have found that issues with structures that have failed usually are not the responsibility of the engineer who designed it but of the person in charge of the project finances.
Those that hold the purse strings seem to find ways to cut corners regardless of the outcome.Leave a comment:
-
Bad engineering has been with us since there was engineering. Nothing new there. Small and large failures have been and always will be with us.Agree that this system will be the cause of a lot of woe. But bad engineering has been with us for a long time. Consider -
- A line of cars in 1970's (Buick Skyhawk, Chevy Monza, Pontiac Sunbird, Olds Starfire) that required partial removal of the engine to change the spark plugs
- The Hyatt Regency walkway collapse in '81 (killed 114.) Engineers at Havens Steel had found a way to "simplify" assembly of the walkway.
- The Tacoma Narrows bridge collapse in 1940.
- The Tay Bridge collapse in 1879. Killed about 80 people. The engineer, Thomas Bouche, had found a way to save some money on bracing.
- Challenger in 1986, due to a flaw known about since 1977.
Maybe this racking fixing method is no more than another example of what I'd call a lack of good engineering.
1.) Looks to me like an attempt was made to find a fixing/attachment method by people who had incomplete knowledge of the forces/moments and loadings involved. Then, an easier (read quicker) and cheaper method was found that did not consider the long term effects of those things. Yea, happens all the time.
2.) I'm not implying you are giving anyone a pass here, but because bad engineering happens all the time is no reason to give it a pass when it occurs in situations such as this.
3.) My guess is that a lot of tile hooks on roofs will be just fine, but most of that OKness will be the result of the conservative assumptions and methods that are used to estimate design loads such as wind speeds that may never occur, or embedment lengths for lag screws, etc., or any number of other such things. Some of what I've seen as an engineer gave me a greater appreciation for things like factors of safety, but also continues to make me wonder just how much more of what passes for today's engineering is chewing into that built in conservativeness than prior engineering chewed into that conservativeness.
As a semi qualitative statement, IMO only, tile hooks are probably marginally adequate, but the probability of failures with tile hooks will be higher than other methods.
Leave a comment:
-
Agree that this system will be the cause of a lot of woe. But bad engineering has been with us for a long time. Consider -
- A line of cars in 1970's (Buick Skyhawk, Chevy Monza, Pontiac Sunbird, Olds Starfire) that required partial removal of the engine to change the spark plugs
- The Hyatt Regency walkway collapse in '81 (killed 114.) Engineers at Havens Steel had found a way to "simplify" assembly of the walkway.
- The Tacoma Narrows bridge collapse in 1940.
- The Tay Bridge collapse in 1879. Killed about 80 people. The engineer, Thomas Bouche, had found a way to save some money on bracing.
- Challenger in 1986, due to a flaw known about since 1977.
Leave a comment:
-
It isn't so much the tendency to lift (or the downward wind loading) as it is the cyclic and fatigue stress that will loosen the system and increase the amplitude of the occasional/cyclic wind loading that I'd be more worried about. That may be what happened in the OP's case.JPM, I thought about that when I was doing mine, I used tilehooks similar to the ones shown here, and although the design calcs were based on two screws that would each take x amount of pull to pull out of the wood and share the load equally (on paper), I knew that the lever would reduce the load capability, and even more so because the screws wouldn't share the load equally; the screw nearest the arm would pull first, the second screw would take the load only after the threads in the first screw had failed. I over-engineered it for that reason, but never felt good about that aspect of the design. If I were in the OP's shoes I might consider adding a few mounts to (hopefully) reduce the tendency to lift.
Seemed to me when looking at the tile hook design a number of years ago I was reminded of a can opener and wondered if anyone was really thinking about or even knew what the design requirements might be, or just some moron(s) who think they're engineers because they can operate software were merely looking for a cheap and fast attachment system.
I came to the conclusion it's an example and a sign of the times, and a harbinger of that way engineering is going.Leave a comment:
-
JPM, I thought about that when I was doing mine, I used tilehooks similar to the ones shown here, and although the design calcs were based on two screws that would each take x amount of pull to pull out of the wood and share the load equally (on paper), I knew that the lever would reduce the load capability, and even more so because the screws wouldn't share the load equally; the screw nearest the arm would pull first, the second screw would take the load only after the threads in the first screw had failed. I over-engineered it for that reason, but never felt good about that aspect of the design. If I were in the OP's shoes I might consider adding a few mounts to (hopefully) reduce the tendency to lift.Last edited by sdold; 12-07-2018, 01:35 AM.Leave a comment:
Copyright © 2014 SolarReviews All rights reserved.
Powered by vBulletin® Version 6.1.3
Copyright © 2026 MH Sub I, LLC dba vBulletin. All rights reserved.
Copyright © 2026 MH Sub I, LLC dba vBulletin. All rights reserved.
All times are GMT-5. This page was generated at 12:10 PM.
Leave a comment: