    Information on solar lighting

    We are planning to place solar lighting in our Society (around 150 flats). We are located in India (Maharashtra). I have some basic queries regarding solar energy option. Any help (references etc.) are welcome.
    My queries are
    * What is the amount for solar installation?
    * What is break even period for the amount?
    * Is there any government subsidy available for this? If yes how much is it?
    * How much time is required for installation of such system?
    * what is maintenance cost of such a system? Is it too high?

    thanks
    Vishal.
  • Mike90250
    Moderator
    • May 2009
    • 16020

    #2
    * What is the amount for solar installation?
    Varys depending on your local labor rates for roof and electrical work


    * What is break even period for the amount?
    Depends on how much you spend, vs how much you currently pay
    about 7-20 years roughly, in the United States


    * Is there any government subsidy available for this? If yes how much is it?
    Check with your local officials


    * How much time is required for installation of such system?
    Skilled installers (4 people) can install a 10KW system in 2 days.

    * what is maintenance cost of such a system? Is it too high?
    Pure Grid Intertie solar:
    wash dust off the panels every 60 days
    replace inverter every 10 years @ $5,000 US

    Battery based:
    wash dust off the panels every 60 days
    replace inverter every 10 years @ $5,000 US
    add distilled water every month
    inspect tighten battery cables every 6 months
    replace battery bank every 7 years
    Powerfab top of pole PV mount (2) | Listeroid 6/1 w/st5 gen head | XW6048 inverter/chgr | Iota 48V/15A charger | Morningstar 60A MPPT | 48V, 800A NiFe Battery (in series)| 15, Evergreen 205w "12V" PV array on pole | Midnight ePanel | Grundfos 10 SO5-9 with 3 wire Franklin Electric motor (1/2hp 240V 1ph ) on a timer for 3 hr noontime run - Runs off PV ||
    || Midnight Classic 200 | 10, Evergreen 200w in a 160VOC array ||
    || VEC1093 12V Charger | Maha C401 aa/aaa Charger | SureSine | Sunsaver MPPT 15A

    solar: http://tinyurl.com/LMR-Solar
    gen: http://tinyurl.com/LMR-Lister

    Comment

    Working...