Hello everyone,
I have a question about ToU rates on SDGE NEM2.0 customers who are on DR-SES plan. I am sorry if this was discussed and explained before.
If the system generates more power than used at the end of true-up period, being on Tiered plan or ToU does not matter, except you have to pay non-by-passable charges. Is that statement correct?
----
Can you review the examples below and see if my understanding is correct?
Example 1)
Annual Household consumption: 6000kWhr
Annual Solar Generation: 6000kWhr
True up cost = Non Bypassable Charges($10?) * 12 = $120 total cost.
Example 2)
Annual HouseHold Consumption: 5400kWhr
Annual Solar Generation: 6000 KWhr
Overgeneration: SDGE pays 2 cents(?) for extra generation = 600kWh * 0.02 = $120
True-up Cost = 0
Example 3)
Annual Household Consumption = 7000kWhr
Annual Solar Generation: 6000kWhr
Excess consumption is during semi-peak hours summer evenings 6-10pm on DR-SES costs $0.25 per kWhr
Total bill at true up is 1000 * $0.25 (excess usage) + NBC ($120) = $370.
---
And last question I have is can I assume $10 NBC on average per month?
Thanks for your help!