Hello,
I'm back for more help. This time with pictures.
Here are my mounts. Home made. There is bedrock 1 foot down in places and 6 foot down in others so I made slabs for each pier so they can float with the frost heave. Winters are extreme. Used wood instead of metal due to cost. The metal prices were outrageous to get it where I am at. Those concrete blocks are 4 foot by 5 foot and 18 inches thick. It was 10 yards of concrete. Full truck worth. The wood is all 6x6 and is very heavy! I will be using paint and EPDM to put a barrier between the aluminum and the wood for corrosion issues. There are no inspection type issues I am as remote as you can get with power.
The complete run of all 10 pads is 160 Feet
Wire Trench - The Trench is 107 feet from the corner of the closest pier to the front corner of the building - The breaker box (electric panel) is in the front corner while the meter/ac disconnect is on the back corner on the same side of the building. Building is 60ft long on that side so 60ft between meter and the electric box.
Here is the current Meter + Ac Disconnect that was installed by the electrician when the power was first put in. The grounding electrode is in the ground right below the panel.
** I am not planning on hooking this up on my own. I will be calling the same electrician that put the service in to do final hook ups. I would like to go 99.99% of the the way though before he gets there. I'm having issues understanding a few of concepts so its making pre-running the wire a bit difficult. The forum got me past my first hurdle a couple days ago and I'm coming back for seconds if you guys are still available. Your info really helped me out.
(3) SMA 6300 watt inverters (4 dc inputs possible - maxes out at 600 volts) - incorporated dc disconnect
(60) Hyundai 45.1 volt 8.8 amp panels
Using 10 AWG pv wire
Wiring in series
10 panels per string
2 strings per inverter
6 strings total.
grid-tie
Question 1
My plan currently is to run each string straight to the inverter (incorporated dc disconnect). No junction boxes, combiners, fuses, breakers. Each string gets a line straight from its last panel to its own input on the inverter with nothing in between. 451 volts and 8.8amps. This is a lot of wire obviously. Is there a better way to save on wire or is it better to keep it the way I'm planning. . Any disasters ahead? Missing something completely? Boneheaded?
Question 2
Grounding: I'm using the old school lug method (tin coated) as I have no rails for weeb or other fancy options. To be honest I'm completely confused on the grounding front. Once all the panels are connected with the grounding wire where is its first stop? To the rod in the ground under the meter or into the inverter? If the answer is rod in the ground should I use the one close to the building or should I put one out in the field somewhere? If I go from panels to rod in the field does it need to work back to the ground rod at the building or it terminated in the field? Is 6 AWG what is needed for the job?
Question 3
What is the path the AC current takes after the inverter. I'm not sure if I go from the inverter to my breaker box or if it goes to the current AC disconnect or if I need a 2nd separate AC disconnect. Can you give me an idea on the equipment that AC currnet hits (in order) as the power runs through the AC side with this setup.
Planning on using 10 awg and 30 amp breakers. I have 15 open slots on my panels 200 service.
Thanks again for everything
I'm back for more help. This time with pictures.
Here are my mounts. Home made. There is bedrock 1 foot down in places and 6 foot down in others so I made slabs for each pier so they can float with the frost heave. Winters are extreme. Used wood instead of metal due to cost. The metal prices were outrageous to get it where I am at. Those concrete blocks are 4 foot by 5 foot and 18 inches thick. It was 10 yards of concrete. Full truck worth. The wood is all 6x6 and is very heavy! I will be using paint and EPDM to put a barrier between the aluminum and the wood for corrosion issues. There are no inspection type issues I am as remote as you can get with power.
The complete run of all 10 pads is 160 Feet
Wire Trench - The Trench is 107 feet from the corner of the closest pier to the front corner of the building - The breaker box (electric panel) is in the front corner while the meter/ac disconnect is on the back corner on the same side of the building. Building is 60ft long on that side so 60ft between meter and the electric box.
Here is the current Meter + Ac Disconnect that was installed by the electrician when the power was first put in. The grounding electrode is in the ground right below the panel.
** I am not planning on hooking this up on my own. I will be calling the same electrician that put the service in to do final hook ups. I would like to go 99.99% of the the way though before he gets there. I'm having issues understanding a few of concepts so its making pre-running the wire a bit difficult. The forum got me past my first hurdle a couple days ago and I'm coming back for seconds if you guys are still available. Your info really helped me out.
(3) SMA 6300 watt inverters (4 dc inputs possible - maxes out at 600 volts) - incorporated dc disconnect
(60) Hyundai 45.1 volt 8.8 amp panels
Using 10 AWG pv wire
Wiring in series
10 panels per string
2 strings per inverter
6 strings total.
grid-tie
Question 1
My plan currently is to run each string straight to the inverter (incorporated dc disconnect). No junction boxes, combiners, fuses, breakers. Each string gets a line straight from its last panel to its own input on the inverter with nothing in between. 451 volts and 8.8amps. This is a lot of wire obviously. Is there a better way to save on wire or is it better to keep it the way I'm planning. . Any disasters ahead? Missing something completely? Boneheaded?
Question 2
Grounding: I'm using the old school lug method (tin coated) as I have no rails for weeb or other fancy options. To be honest I'm completely confused on the grounding front. Once all the panels are connected with the grounding wire where is its first stop? To the rod in the ground under the meter or into the inverter? If the answer is rod in the ground should I use the one close to the building or should I put one out in the field somewhere? If I go from panels to rod in the field does it need to work back to the ground rod at the building or it terminated in the field? Is 6 AWG what is needed for the job?
Question 3
What is the path the AC current takes after the inverter. I'm not sure if I go from the inverter to my breaker box or if it goes to the current AC disconnect or if I need a 2nd separate AC disconnect. Can you give me an idea on the equipment that AC currnet hits (in order) as the power runs through the AC side with this setup.
Planning on using 10 awg and 30 amp breakers. I have 15 open slots on my panels 200 service.
Thanks again for everything
Comment