My solar system has been installed and turned on. I didn't see many topics on how long it takes to get a system installed before my install started. Below is a timeline for reference for my install in the city of Chula Vista, a suburb of San Diego. My installer says that county permitting in unincorporated cities takes only a day or two. Chula Vista is 2-3 weeks, which is what mine took. He said his experience is that Poway is the slowest.
3/18 Signed contract
3/21 Permit request created
3/22 Permit submitted to city
4/7 City requires permit modification
4/15 Permit approved by city
4/16-20 Installation
4/21 City inspects and approves project
4/22 SDG&E received city approval
4/27 SDG&E permission to turn on system
3/18 Signed contract
3/21 Permit request created
3/22 Permit submitted to city
4/7 City requires permit modification
4/15 Permit approved by city
4/16-20 Installation
4/21 City inspects and approves project
4/22 SDG&E received city approval
4/27 SDG&E permission to turn on system