I just had my ground mount system installed,
received the following working in the email from SDGE:
"This e-mail is to inform you that your City/County inspection has been received and is being processed by San Diego Gas & Electric's Net Energy Metering Department.The next step is for SDG&E to inspect your solar system. We will conduct your inspection within the next two weeks.
Please note: customers do not need to be present for our field inspection. We will be inspecting your electric meter only.
As a reminder, your solar system cannot operate until you receive notification from SDG&E (please refer to 3.2 of the Interconnection Agreement below)."
a. why they need two weeks to inspect the freaking meter?
b. is it going to be productive to sit on their tail and ask them every day why it's not inspected yet?
Thanks!
received the following working in the email from SDGE:
"This e-mail is to inform you that your City/County inspection has been received and is being processed by San Diego Gas & Electric's Net Energy Metering Department.The next step is for SDG&E to inspect your solar system. We will conduct your inspection within the next two weeks.
Please note: customers do not need to be present for our field inspection. We will be inspecting your electric meter only.
As a reminder, your solar system cannot operate until you receive notification from SDG&E (please refer to 3.2 of the Interconnection Agreement below)."
a. why they need two weeks to inspect the freaking meter?
b. is it going to be productive to sit on their tail and ask them every day why it's not inspected yet?
Thanks!