I installed a Sunny Boy 7.7-US today and the following caught my attention in the Commissioning section of the installation manual:
Configure the inverter. Please note that the personal
SMA Grid Guard code for changing the grid-relevant parameters
must be available after completion of the first ten
feed-in hours (see "Application for the SMA Grid Guard
code" available at www.SMA-Solar.com).
I'm in the US and purchased the inverter from a large US seller, so I don't anticipate needing to change the grid parameter, unless they are not already set to US.
I have the unit mounted and powered up, but the web interface is limited in functionality until the inverter comes on-line, which will be Tuesday when I install the panels (not here yet).
Just curious if I need to submit an application for this code. There's a 59 Euro fee as well.
Thanks
Configure the inverter. Please note that the personal
SMA Grid Guard code for changing the grid-relevant parameters
must be available after completion of the first ten
feed-in hours (see "Application for the SMA Grid Guard
code" available at www.SMA-Solar.com).
I'm in the US and purchased the inverter from a large US seller, so I don't anticipate needing to change the grid parameter, unless they are not already set to US.
I have the unit mounted and powered up, but the web interface is limited in functionality until the inverter comes on-line, which will be Tuesday when I install the panels (not here yet).
Just curious if I need to submit an application for this code. There's a 59 Euro fee as well.