"Solar Roofing Best Practices - Low Slope Roofs presented on 5/26/2015 by Jeff Spies
http://www.quickmountpv.com/support/...e-webinar.html
They make a pretty strong case for the QuickMount system (obviously that is what they sell)"
I contend these guys are taking the solar industry down their yellow-brick-road.
In the webinar I've seen from them, they pull out nails from shingles in order to get their flashing way up under, then advise using a bit of sealer to seal the hole left by the nails! We're working on getting statements from some roofing manufacturers to refute these guys.BSEE, R11, NABCEP, Chevy BoltEV, >3000kW installedComment
-
As long as no water pools around the wood footing it should last a while.
Moisture is incredibly destructive when it stays in contact with just about anything from metal (rust) to concrete (breakdown from acidity).
Stay high and dry and live long and prosper.
Comment
-
It is a low slope; The AC unit is straddling the peak. I put a level on it and they almost got it level. Maybe a 1/8" out on my 24" level.
Is that 5 mrad?Comment
-
water doesn't last long around here including wood moisture; it need to be pressure treated.Comment
Copyright © 2014 SolarReviews All rights reserved.
Powered by vBulletin® Version 6.1.3
Copyright © 2025 MH Sub I, LLC dba vBulletin. All rights reserved.
Copyright © 2025 MH Sub I, LLC dba vBulletin. All rights reserved.
All times are GMT-5. This page was generated at 04:35 PM.
Comment