Hi folks,
A question about backfeeding a subpanel vs. main service panel. I've searched the indexes and found a few similar threads, but not quite the same. Thought I'd throw this out there for opinions.
I'm taking bids on a ~9.1 Kw Grid-Tie (only) solar array that will be mounted on the backside of my shop, not my actual house roofline. The panels will be approximately 180' from my main service meter (and main service panel). The main service panel is a 200 amp service, with a 60 amp breaker that feeds a 200 amp sub-panel in the shop near where the solar panels will be installed. I believe the copper feeding the subpanel is #4 or #6, but I'll have to verify for sure. It is definately larger than #8 though.
My question is... Can I backfeed the subpanel with the 9.1 Kw array? Or do I need to bury another run of dedicated copper all the way up to the main panel/meter? Is there some reason I would NOT want to do this? Code? Safety?
One more consideration, I plan on installing a transfer switch somewhere in the system for a (future) ~12-14Kw propane generator. Where would this fit into the system so the generator and panels don't fry each other? (I know they can't work together)
I can mount that generator either up by the house or back by the shop, but the bulk propane tank will have to be back by the shop due to some physical space limitations of keeping the propane tank away from electrical sources and buildings. I may have to bury a LP fuel line for that run. Those are some logisitics I can work out later.
Thanks for any input.
Jim
A question about backfeeding a subpanel vs. main service panel. I've searched the indexes and found a few similar threads, but not quite the same. Thought I'd throw this out there for opinions.
I'm taking bids on a ~9.1 Kw Grid-Tie (only) solar array that will be mounted on the backside of my shop, not my actual house roofline. The panels will be approximately 180' from my main service meter (and main service panel). The main service panel is a 200 amp service, with a 60 amp breaker that feeds a 200 amp sub-panel in the shop near where the solar panels will be installed. I believe the copper feeding the subpanel is #4 or #6, but I'll have to verify for sure. It is definately larger than #8 though.
My question is... Can I backfeed the subpanel with the 9.1 Kw array? Or do I need to bury another run of dedicated copper all the way up to the main panel/meter? Is there some reason I would NOT want to do this? Code? Safety?
One more consideration, I plan on installing a transfer switch somewhere in the system for a (future) ~12-14Kw propane generator. Where would this fit into the system so the generator and panels don't fry each other? (I know they can't work together)
I can mount that generator either up by the house or back by the shop, but the bulk propane tank will have to be back by the shop due to some physical space limitations of keeping the propane tank away from electrical sources and buildings. I may have to bury a LP fuel line for that run. Those are some logisitics I can work out later.
Thanks for any input.
Jim
Comment