I am looking for a bit of reassurance - or a dope slap if necessary - on how I intend to proceed on a Enphase M250 installation .
For several reasons (available daylight, available time, weather, etc.) I intend to install 20 Enphase M250 micro inverters and 20 Solarworld 280W panels (two branch circuits) today and terminate them at an AC sub panel in my attic - then when I have time I will run wire from the main load panel through an AC disconnect up to the AC subpanel in the attic.
This would be out of sequence per the enphase installation manual - but I can't see any harm in doing it this way. Any thoughts on problems I may be opening myself up to would be appreciated!
For several reasons (available daylight, available time, weather, etc.) I intend to install 20 Enphase M250 micro inverters and 20 Solarworld 280W panels (two branch circuits) today and terminate them at an AC sub panel in my attic - then when I have time I will run wire from the main load panel through an AC disconnect up to the AC subpanel in the attic.
This would be out of sequence per the enphase installation manual - but I can't see any harm in doing it this way. Any thoughts on problems I may be opening myself up to would be appreciated!