  • Mike 134
    Solar Fanatic
    • Jan 2022
    • 385

    #16
    Just an update
    Received my "permission to operate" today from the power company so almost done.
    Now I need to apply for the Illinois residential energy credits, which is the only reason at 65 years old I did this project. Didn't see a value in it without the "refund" from the state.

    Overall the front end paperwork was the worst part of the project, rest was easy.
    Attached Files
    Last edited by Mike 134; 05-06-2022, 08:56 PM.

    Comment

    • Mike90250
      Moderator
      • May 2009
      • 16020

      #17
      Originally posted by Mike 134
      ...... Tried to upload a few pictures but kept getting an error message???
      Most pics need to have their size ( resolution ) knocked down quite a bit, before posting to a message board. My phone takes pics that
      are 4Mb, but knocked down to 500Kb, they are fine for messages

      Powerfab top of pole PV mount (2) | Listeroid 6/1 w/st5 gen head | XW6048 inverter/chgr | Iota 48V/15A charger | Morningstar 60A MPPT | 48V, 800A NiFe Battery (in series)| 15, Evergreen 205w "12V" PV array on pole | Midnight ePanel | Grundfos 10 SO5-9 with 3 wire Franklin Electric motor (1/2hp 240V 1ph ) on a timer for 3 hr noontime run - Runs off PV ||
      || Midnight Classic 200 | 10, Evergreen 200w in a 160VOC array ||
      || VEC1093 12V Charger | Maha C401 aa/aaa Charger | SureSine | Sunsaver MPPT 15A

      solar: http://tinyurl.com/LMR-Solar
      gen: http://tinyurl.com/LMR-Lister

      Comment

      • Mike 134
        Solar Fanatic
        • Jan 2022
        • 385

        #18
        Originally posted by Mike90250

        Most pics need to have their size ( resolution ) knocked down quite a bit, before posting to a message board. My phone takes pics that
        are 4Mb, but knocked down to 500Kb, they are fine for messages
        thank you resized and works

        Comment

        • foggysail
          Solar Fanatic
          • Sep 2012
          • 123

          #19
          GEES---- looks greaaat Mike!!!

          Comment

          • bcroe
            Solar Fanatic
            • Jan 2012
            • 5198

            #20
            I paid my money and got permission to build 15KW in 2013 in IL.
            BUT they did not come over and install the 2 way electric meter,
            WHY IS THAT? I dodged the paperwork by hiring an installer,
            how much damage could he do 500 feet behind my house?
            But after the system was inspected and approved, the essential
            meter was not installed for another 6 weeks. I hounded the local
            support and discovered it had not even been ordered. My estimate
            of this prime season loss approached $1000. But I got even later.

            Please let us know the delay for your IL PV system operation. It
            seems to me, as soon as you pay and get a permit, a Net meter
            needs to go in. Bruce Roe

            Comment

            • Mike 134
              Solar Fanatic
              • Jan 2022
              • 385

              #21
              Originally posted by bcroe

              Please let us know the delay for your IL PV system operation. It
              seems to me, as soon as you pay and get a permit, a Net meter
              needs to go in. Bruce Roe
              Smart meters were installed last year throughout the neighborhood so that is already done. I'm curious if I'll still get rebates from ComEd for reducing my power usage during certain times when they send a text message like last year. I think it was 4 times got credits of $35 but hey better than a poke in the eye.
              I was surprised last month when I pulled the meter to upgrade the panel Edison texted me about an hour after I started and wanted to know if I needed a lineman because my power was off.


              Comment