So we have a client that has this rigged up solar setup to remote view the top of the landfill. Apparently the solution works for a few days then needs to be reset and fires up again. The goal of this is to power an access point and PTZ camera whenever possible but also to have it be low maintenance (auto power on when resources are available and power off/charge when depleted). Any pointers/recommendations to make this happen would be great. Appears to be (2) 100w panels, Hykolity 12V 100AH Deep Cycle AGM SLA VRLA Battery, P20L controller, WindyNation 1500w Inverter Thanks for any help!