Daily needs: 1.09 kWh, Solar zone 2 (SE Utah)
I'd be appreciative of any input on the off-grid system below, and have three main questions right now:
1) do I need a remote inverter controller? The wholesaler I'm buying from recommends it (specifically the Magnum Energy ME-ARC Inverter Remote), they say the inverter (Magnum Energy MMS1012G) needs to be reprogrammed for most folks use
2) The panels will be 50 ft from the structure where energy will be consumed. What would be the best distances to configure? For example, keep everything at the panels, run a cable to the structure - or house everything there
3) What is the proper application / place for breakers? One between charge controller and batteries and then between panels and the controller?
Thank you in advance for your time!
I'm planning to purchase & install this system:
Magnum Energy MMS1012G Inverter
4 Solarland SLP160S-12 Silver Mono Solar Panel
Four Star Solar MC4 Unlocking Tool
Four Star Solar MC4 10 AWG - 100' Cable Extension
Four Star Solar 2/0 - 96" UL Cable (White)
Four Star Solar 2/0 - 60" UL Cable (Red)
Four Star Solar 2/0 - 36" UL Cable (Red)
? *Magnum Energy ME-ARC Inverter Remote
MidNite Solar MNBCM battery capacity meter
MidNite Solar MNEPV-60 Breaker MidNite Solar MNEPV 15 amp 150VDC din rail mount breaker
Morningstar Corporation TriStar TS-MPPT-45 Charge Controller MidNite Solar MNDC125 Breaker Box Morningstar Corporation TriStar Controller TS-M-2 Display
2 Crown AGM 220 Ah 12 VDC 2,640 Wh (2) Batteries
Daily needs: 1.09 kWh, Solar zone 2 (SE Utah)
I'd be appreciative of any input on the off-grid system below, and have three main questions right now:
1) do I need a remote inverter controller? The wholesaler I'm buying from recommends it (specifically the Magnum Energy ME-ARC Inverter Remote), they say the inverter (Magnum Energy MMS1012G) needs to be reprogrammed for most folks use
2) The panels will be 50 ft from the structure where energy will be consumed. What would be the best distances to configure? For example, keep everything at the panels, run a cable to the structure - or house everything there
3) What is the proper application / place for breakers? One between charge controller and batteries and then between panels and the controller?
Thank you in advance for your time!
I'm planning to purchase & install this system:
Magnum Energy MMS1012G Inverter
4 Solarland SLP160S-12 Silver Mono Solar Panel
Four Star Solar MC4 Unlocking Tool
Four Star Solar MC4 10 AWG - 100' Cable Extension
Four Star Solar 2/0 - 96" UL Cable (White)
Four Star Solar 2/0 - 60" UL Cable (Red)
Four Star Solar 2/0 - 36" UL Cable (Red)
? *Magnum Energy ME-ARC Inverter Remote
MidNite Solar MNBCM battery capacity meter
MidNite Solar MNEPV-60 Breaker MidNite Solar MNEPV 15 amp 150VDC din rail mount breaker
Morningstar Corporation TriStar TS-MPPT-45 Charge Controller MidNite Solar MNDC125 Breaker Box Morningstar Corporation TriStar Controller TS-M-2 Display
2 Crown AGM 220 Ah 12 VDC 2,640 Wh (2) Batteries