    Is Panel possible with current setup

    i have a 500VA inverter with a 12V 100AH Battery which charges from AC mains (220V). Is it possible for me to have a 100 W solar panel with a suitable battery charge controller to charge the above battery with optional charging from mains. i am just one month old to solar so pls excuse if it is a stupid question.
  • Mike90250
    Moderator
    • May 2009
    • 16020

    #2
    Welcome.

    A 100w panel, if it is voltage matched to your system, would take several hours of sunlight to recharge the 100a battery. It would be slow, but not impossible.
    Powerfab top of pole PV mount (2) | Listeroid 6/1 w/st5 gen head | XW6048 inverter/chgr | Iota 48V/15A charger | Morningstar 60A MPPT | 48V, 800A NiFe Battery (in series)| 15, Evergreen 205w "12V" PV array on pole | Midnight ePanel | Grundfos 10 SO5-9 with 3 wire Franklin Electric motor (1/2hp 240V 1ph ) on a timer for 3 hr noontime run - Runs off PV ||
    || Midnight Classic 200 | 10, Evergreen 200w in a 160VOC array ||
    || VEC1093 12V Charger | Maha C401 aa/aaa Charger | SureSine | Sunsaver MPPT 15A

    solar: http://tinyurl.com/LMR-Solar
    gen: http://tinyurl.com/LMR-Lister

    Comment

    • Naptown
      Solar Fanatic
      • Feb 2011
      • 6880

      #3
      Yes it will work
      NABCEP certified Technical Sales Professional

      [URL="http://www.solarpaneltalk.com/showthread.php?5334-Solar-Off-Grid-Battery-Design"]http://www.solarpaneltalk.com/showth...Battery-Design[/URL]

      [URL]http://www.calculator.net/voltage-drop-calculator.html[/URL] (Voltage drop Calculator among others)

      [URL="http://www.gaisma.com"]www.gaisma.com[/URL]

      Comment

      • sanjith
        Junior Member
        • Jun 2012
        • 2

        #4
        how long

        how long it may take, as per my knowledge 8 hours is enough, right?
        Originally posted by Mike90250
        Welcome.

        A 100w panel, if it is voltage matched to your system, would take several hours of sunlight to recharge the 100a battery. It would be slow, but not impossible.

        Comment

        • Naptown
          Solar Fanatic
          • Feb 2011
          • 6880

          #5
          Originally posted by sanjith
          how long it may take, as per my knowledge 8 hours is enough, right?
          That will depend on the insolation and depth of discharge and to some extent the type of charge controller.
          NABCEP certified Technical Sales Professional

          [URL="http://www.solarpaneltalk.com/showthread.php?5334-Solar-Off-Grid-Battery-Design"]http://www.solarpaneltalk.com/showth...Battery-Design[/URL]

          [URL]http://www.calculator.net/voltage-drop-calculator.html[/URL] (Voltage drop Calculator among others)