    Originally posted by newe70
    Congrats!!! That is not bad. SCE down here would takes around 2-3 weeks to give a pto. My NEM application is to be sent today or tomorrow. City Inspector gave a green light to go this morning.
    It is just an estimate from couple guys ... PGE states it should be done in 5-7 business days, but no longer than 30 days.

    Comment

    • solar_newbie
      Junior Member
      • Aug 2015
      • 406

      #47
      EV car charger connected... All are final.

      Pictures of the electric connection. This can be example if someone do not want to pay for the sub-panel upgrade. Ask to include the second sub for free as you pay too much labor for solar. I am not sure how much times for upgrading sub-panel, but it is kind of similar job-- move AC connector, add new sub-panel, run conduit and install EV car charger ... Cost at more than 5 hours total.

      Main panels with 2 breakers : 100A for existing sub-panel of the house, 60A breaker for a new sub-panel for solar.
      Special label must states "Solar sub-panel to the right over the fence" Really specific to the location.
      image.jpg
      image.jpg

      New Sub-panel has 4 breakers : 2 15Amp for 2 Enphase strings, 1 40A for AC and 1 40A for EV car charger.
      image.jpg
      image.jpg

      EV car charger connected today _ Bosch Power Max 30A 240V 18 feet cable . Price $90 (after $500 credit from GM for spark EV)
      image.jpg

      All jobs are done as contract.... The rest is to wait for PG&E plus future production ...

      Comment

      • solar_newbie
        Junior Member
        • Aug 2015
        • 406

        #48
        Envoy and rainforest eagle

        Here is picture on how I connect envoy and rainforest eagle in garage.
        - Envoy use wifi usb to connect to Internet.
        - Rainforest Aegle connect to the WIFI extender next to it using CAT-5 (Rainforest must be few feet from meter ... That is the limited of the smart meter -- you can do the same way for connecting Solaredge to Internet)

        image.jpeg

        Comment

        • foo1bar
          Solar Fanatic
          • Aug 2014
          • 1833

          #49
          Originally posted by solar_newbie
          Pictures of the electric connection.
          What brand is your main panel (with the meter)?

          It looks to me like might be federal pacific.
          (I couldn't read the writing on the cover in the picture.)

          If it's federal pacific, I'd strongly consider replacing it as part of your solar install.

          Comment

          • solar_newbie
            Junior Member
            • Aug 2015
            • 406

            #50
            Originally posted by foo1bar
            What brand is your main panel (with the meter)?

            It looks to me like might be federal pacific.
            (I couldn't read the writing on the cover in the picture.)

            If it's federal pacific, I'd strongly consider replacing it as part of your solar install.
            I do not know. Since the smart meter is a part of the panel. I would assume it is PG&E side. The main panel replacement is a big job since it involve to move the underground power core (200A) to couple feet plus coordination with PG&E to turn off power and move the underground supply. Plus the main panel is 200A already. The rule is not to have power and gas pipe close to each other.

            Unless it has problem, there is no reason to do so.

            Comment

            • foo1bar
              Solar Fanatic
              • Aug 2014
              • 1833

              #51
              Originally posted by solar_newbie
              I do not know. Since the smart meter is a part of the panel. I would assume it is PG&E side. The main panel replacement is a big job since it involve to move the underground power core (200A) to couple feet plus coordination with PG&E to turn off power and move the underground supply. Plus the main panel is 200A already. The rule is not to have power and gas pipe close to each other.
              The meter is PG&E property, but the socket/main panel is yours.

              Have you checked with your AHJ and PG&E about whether replacing the panel would require moving the underground feeder?
              It is likely that even if they are too close they'd let you get away with it as a grandfathered install even when replacing the main panel.
              But since I don't see a gas pipe/meter in the picture it's hard to say if they even are too close for a current install.

              Unless it has problem, there is no reason to do so.
              If it's federal pacific it IS a problem.
              Look at the panel for who makes it and then go from there.
              If it were me and it was federal pacific, I'd replace it - even if it was $2-4K.

              Comment

              • solar_newbie
                Junior Member
                • Aug 2015
                • 406

                #52
                Originally posted by foo1bar
                The meter is PG&E property, but the socket/main panel is yours.

                Have you checked with your AHJ and PG&E about whether replacing the panel would require moving the underground feeder?
                It is likely that even if they are too close they'd let you get away with it as a grandfathered install even when replacing the main panel.
                But since I don't see a gas pipe/meter in the picture it's hard to say if they even are too close for a current install.



                If it's federal pacific it IS a problem.
                Look at the panel for who makes it and then go from there.
                If it were me and it was federal pacific, I'd replace it - even if it was $2-4K.
                It is Arrow Hart Murray. I just check it. It shows on the front door.
                It looks dirty outside, but internal is still pretty good (no damage or rust ...) Cable is also looks good , along with all connections.

                Comment

                • solar_newbie
                  Junior Member
                  • Aug 2015
                  • 406

                  #53
                  PTO received

                  Finally the whole solar transaction is done. PTO email is received today. It seems PG&E really working hard. It takes 3 business days to complete the transaction (submit on 10/7, accept on 10/12)...
                  This thread is end here ... Update the main thread for the whole process.

                  Comment

                  • newe70
                    Member
                    • Aug 2015
                    • 78

                    #54
                    Congrats...your solar project is moving really super quick. Now, just sit back and enjoy the cleaned power for years to come. Im hoping to have a pto in the next 2-3 weeks for, SCE.

                    Comment

                    • solardreamer
                      Solar Fanatic
                      • May 2015
                      • 446

                      #55
                      Originally posted by solar_newbie
                      Finally the whole solar transaction is done. PTO email is received today. It seems PG&E really working hard. It takes 3 business days to complete the transaction (submit on 10/7, accept on 10/12)...
                      This thread is end here ... Update the main thread for the whole process.
                      Congrats. If you don't mind, please post your findings on solar and E-6 when you have some data. Thanks.

                      Comment

                      • solar_newbie
                        Junior Member
                        • Aug 2015
                        • 406

                        #56
                        Originally posted by solardreamer
                        Congrats. If you don't mind, please post your findings on solar and E-6 when you have some data. Thanks.
                        Sure. I will start a new thread. However, I am going to finish the excel sheet to reflex per month usage. So user can just upload their last year usage, plus adding the adjustment from Solar, EV or any new needed to get the current year usage.

                        Comment

                        • almaden
                          Junior Member
                          • Oct 2015
                          • 5

                          #57
                          Could you pm me your installer? Thank you!